[Operation and Maintenance Bulletin] Notice on power supply maintenance of computer room

  

Dear customers
To provide you with more stable server power supply, our company plans to:
10:00-17:00 US time on October 12, 2013 (01:00-08:00 Chinese time on October 13, 2013)
17:00-17:00 on October 22, 2013 (08:00-17:00 on October 23, 2013)
10:00-17:00 US time on October 26, 2013 (01:00-08:00 Chinese time on October 27, 2013)
Carry out batch A/B circuit maintenance for the power supply of the machine room. At that time, the power supply of the cabinet will be interrupted for 5-10 minutes. Please backup the data before the maintenance time. If it still cannot be used normally after the maintenance is completed, please report the problem to our engineer on duty in time, so as to deal with some servers that have not been started automatically. Sorry for the inconvenience, thank you for your support and cooperation.