synonymProject Feasibility Study Report(The report that determines the feasibility of the project with a comprehensive analysis method) Generally refers to the feasibility analysis report
Asinvestment decision The feasibility analysis report is in the previous stageProject ProposalOn the basis of being approved, it mainly conducts an accurate, systematic and complete analysis of the project market, technology, finance, engineering, economy and environment, including market and sales, scale and products, plant siteRaw and auxiliary materialsSupplyProcess technology、Equipment selection, personnel organization, implementation plan, calculation, demonstration and evaluation of investment and cost, benefit and risk, select the best scheme, give conclusive opinions on whether to invest in the development of the project and how to invest, or whether to terminate the investment or continue to invest in the development, etc., provide a scientific basis for investment decisions, and serve as the basis for further work.
Chinese name
Feasibility analysis report
Foreign name
The feasibility study report
importance
Essential key link before investment decision
Content
Market analysis determines the scheme design of available quantity
Preparation department
Professional market research company of Internal Market Department
1. Carry out comprehensive and in-depth market analysis and prediction.Survey and forecastProposed projectProducts in Chinainternational marketSupply and demand and sales price;Research producttarget market, AnalysisMarket share;Study and determine the market, mainly the strengths and weaknesses of product competitors and their own competitiveness, as well as themarketing strategy, and study and determine the mainmarket risk And the degree of risk.
2. For resource development projects, in-depth research should be conducted to determine the available amount of resources, the natural quality of resources, and theOccurrence conditionsAnd development and utilization value.
Feasibility reportThe internal marketing department or professionalMarket research companyWritten by the market research company indata acquisitionThe company has unique professional advantages in data classification, opinion refining and report writing. It is a relatively powerful enterprise in the industry, with a professional report writing team and a complete database.
Project process
Announce
edit
Accept the client's project entrustment → set up a project team → investigate in advance → prepare the projectResearch plan→ Signing contracts or agreements → Formal investigation → Analysis, research, optimization and selection of schemes → Preparation of feasibility analysis report
Explain that the realization of the project is technically, economically andsocial factors The feasibility of the above, comment on the various possible realization schemes that can be selected to reasonably achieve the development goals, and explain and demonstrate the selectedImplementation planReasons.
Key points of preparation
Announce
edit
Detailed projectfeasibility analysis The detailed preparation reference basis mainly includes:
——Relevant national development plans and planning documents.Including relevant regulations on encouragement, licensing, restriction and prohibition of the industry;
——Agreements signed between the project undertaker and relevant parties, such as investment, raw material supplyland used for buildingPreliminary agreement on transportation;
——Relevant national economic laws and regulations.Such as Sino foreign joint venture law, tax, foreign capital, loan and other provisions;National standards, specifications and quota data on construction.
5. Economic Evaluation Methods and Parameters of Construction Projects (Third Edition), reviewed and approved by the National Development and Reform Commission for implementation in 2006;
6. Other domestic and foreign industrial and commercial taxes that the project must comply withlegal documentEtc.
Report Template
Announce
edit
Part I
Project Overview
As the first part of the feasibility study report, the general introduction should comprehensively describe the main problems andresearch conclusionAnd make final suggestions on the feasibility of the project to facilitate the approval of the feasibility study.
In the general part, the main technical and economic indicators in each part of the research report can be summarized and the main technical and economic indicators can be listed, so that the approvers and decision-makers can have a comprehensive understanding of the project.
4、 Existing problems and suggestions
yesfeasibility studyExplain the main problems of the project proposed in and propose solutions.
Part II
Project construction background, necessity and feasibility
This part mainly explains the background of the project, the necessity of investment, the reasons for investment and the implementation of the projectSupportabilityConditions, etc.
Market analysisfeasibility studyThe important position ofChoice of technology、Investment estimationEven the choice of plant site can only be decided after full understanding of market demand.Moreover, the results of market analysis can also determine the product pricesales revenue, which ultimately affects the projectprofitability And feasibility.stayFeasibility study reportThe current market situation should be studied in detail as the basis for later decision-making.
Market forecast is the continuation of market research in time and space. It is based on the information obtained from market researchMarket informationdataanalysis reportThe conclusion ofMarket demandAnd the quantitative and qualitative judgment and analysis of relevant factors.stayfeasibility studyIn the work, the conclusion of market forecast is to formulateProduct planAnd the necessary basis for determining the construction scale of the project.
Project environmental protection and energy conservationLabor safetyprogramme
In the project construction, it is necessary to implement the national environmental protectionEnergy conservationandOccupational safety and healthThe laws and regulations, the possible impact of the project on the environment, and the factors affecting the health and safety of workers should befeasibility studyStage analysis, propose prevention and control measures, and evaluate them,Recommended technologyThe best scheme is feasible, economical, and reasonably distributed, with less harmful impact on the environment.According to the current national regulations, those who engage in activities that have an impact on the environmentConstruction ProjectMust be executedEnvironmental Impact StatementAnd at the same timeFeasibility study reportEnvironmental protection and labor safety should be specifically discussed.
The schedule during project implementation is alsoFeasibility study reportAn important part of.The so-called project implementation period can also be called investment time, which refers to the period from the formal determination of the construction project to the normal production of the project.This period includes project implementation preparation,Fund raisingArrangement,Survey and designandEquipment ordering,Construction preparation, construction andProduction preparation, test run untilCompletion acceptanceAnd delivery for use.Items of these stagesInvestment activitiesSome work links are closely connected with each other, and some work links are carried out at the same time and cross each other.Therefore, in thefeasibility studyStage, it is necessary to plan all work links in each stage of the project implementation,overall balanceAnd make reasonable and practical arrangements.
When evaluating construction projects, most of the data used are from prediction and estimation.Due to the limited data and information, the actual situation in the future may be different from thisinvestment decision It will bring risks.To avoid or minimize risks, it is necessary to analyzeUncertaintyFactor pairProject economic evaluationThe impact of indicators to determine the reliability of the project is called uncertainty analysis.
Financial, economic and social benefits of the project
Under constructiontechnology roadmap After the determination, financialeconomic performanceEvaluate, judge whether the project is economically feasible, and compare and select excellent schemes.The evaluation conclusion in this part is one of the main bases for the selection of the proposed scheme, and also an important basis for the investment decision of the construction project.This part focuses on the financial, economic andSocial benefit evaluationThe main contents of
If the financial net present value of the project is equal to or greater than zero, it indicates that the profitability of the project has reached or exceeded the required profitability, and the project is financially feasible.
Financial internal rate of return refers to the financial performance of the project in each year during the whole calculation periodNet cash flowWhen the sum of the present values of is equal to zeroDiscount rate, that is to make the projectFinancial net present valueDiscount rate when equal to zero.
The calculation of dynamic payback period is based on theCash Flow Statement, calculated with the following approximate formula:
Pt=(cumulativeNet cash flowNumber of years with positive present value - 1)+the present value of accumulated net cash flow of the previous yearabsolute value/Present value of net cash flow in positive years
(2) Evaluation criteria
(1) When Pt ≤ Pc (benchmark investment payback period), it indicates that the project (or scheme) can recover the investment within the required time, which is feasible;
(2) If Pt > Pc, the project (or scheme) is infeasible and should be rejected.
The profit tax rate of project investment refers to that the project reachesDesigned production capacityYear of the next normal production yearTotal profitOr average annual total profit and sales tax and surchargesTotal project investmentThe calculation formula is:
When the investment profit and tax rate is ≥ the average investment profit and tax rate (or benchmark investment profit and tax rate) of the department (industry), the project can be considered acceptable financially.
projectNet profit rate of capitalIt is higher than the reference value of net profit rate of the same industry, indicating thatProject capitalThe profitability expressed by the net profit rate meets the requirements.
(7) Summary of core indicators for project measurement
stayfeasibility studyIn addition to the calculation and analysis of the above indicators, the social benefits and social impacts of the project should also be analyzed, that is, the impact of benefits that cannot be quantified should be qualitatively described.
Part XI
Project risk analysis and risk prevention and control
1、 Construction risk analysis and prevention and control measures
2、 LawPolicy riskAnd prevention and control measures
3、 Market risk and prevention and control measures
5、 Other related risks and prevention and control measures
Part XII
Conclusions and suggestions of project feasibility study
1、 Conclusions and suggestions
According to the research in the previous sectionsAnalysis results, comprehensively evaluate the project technically and economicallyConstruction schemeSummarize and put forward concluding comments and suggestions.Main contents include:
3. Yesfeasibility studyPut forward solutions and suggestions for major problems that have not yet been solved in
4. Explain the main problems of the modification and put forward suggestions for modification
5. For the infeasible project, put forward the infeasible main problems and handling suggestions
6. Conclusions of main controversial issues in the feasibility study
2、 Attachment
Where belongs tofeasibility study of a projectScope, but documents in separate volumes other than the research report shall be listed asFeasibility study reportThe name, date and number of the listed attachments shall be indicated.
1. ForEnterprise financingFeasibility Study Report on Foreign Investment Cooperation
Such research reports usually require accurate market analysisInvestment planReasonable and provide competitive analysisMarketing plan, management planTechnology R&DAnd other practical operation plans.
2. The feasibility study report for the project approval of the National Development and Reform Commission (formerly the Planning Commission).
Among the five kinds of feasibility studies mentioned above, (2), (4) and (5) have the highest entry threshold and require the preparation unit to have the engineering consulting qualification, which is issued by the National Development and Reform Commission and is divided into three grades: Grade A, Grade B and Grade C.
Feasibility study reportAt present, the charging standard of is still the Notice on Printing and Distributing the Interim Provisions on Consulting Fees for Preliminary Work of Construction Projects (JJG [1999] No. 1283) issued by the former National Planning Commission.