[Jiangsu] Construction Organization Design of Municipal Landscape Avenue
Project Overview XX Road Landscape Avenue Project is located at XX Road in the urban area, with a project scale of 6.2km. The project category is municipal, green and garden. This bidding is divided into nine sections, and the construction organization design is the sixth section. The construction organization design shall be prepared according to the construction drawing design content and the requirements of the bidding documents. 1、 Main contents of the project 1 Construction of cofferdam, pumping, desilting and 4m high revetment. 2. Pebble road, polished pebble road and granite road. 3. Anticorrosive wood bench, anticorrosive wood garden bench. 4. 400 wide and 120 wide flower beds. 5. Landscape stone. 6. The earthwork shall be transported and compacted, and the planting soil shall be backfilled and shaped. 7. Drainage and street lamp works. 2、 Project characteristics 1 XX Road Landscape Avenue Project is one of the city image projects. 2. In order to ensure the safety and normal operation of the XX Road Landscape Avenue project, safety is the first priority. Educate the construction personnel to abide by various rules and regulations and not to wander in non operating areas. 3. The area of this greening project is at the roadside of XX, so we pay special attention to civilized construction during construction. 3、 Preparation basis: 1. Bidding Document for Construction of Landscape Avenue Project on XX Road. 2. Construction drawing of XX Road Landscape Avenue Project. 3. Summary of Q&A for the bidding of XX Road Landscape Avenue Project. 4. Code for Construction and Acceptance of Urban Greening Engineering. 5. Technical Operation Specification for Construction of Building Installation Engineering DB32/294-1999 6 In accordance with the provisions of Relevant Civilized Construction Documents. 4、 The project quality bidding document requires that the project quality is qualified, the greening survival rate is more than 100%, and the plant grows well without diseases, pests and weeds. 5、 Construction period The bidding period of the project is from September 20, 2003 to November 20, 2003, and the construction period is 60 days. In order to complete the greening project as soon as possible and reduce the impact of construction on road operation, the bidding period of our company is 60 days. We will use the network diagram to arrange the operation plan, reasonably organize the labor force and allocate sufficient resources, and fully complete the greening construction task on November 20, 2003.