Construction management control scheme of infilled wall masonry
The construction unit shall, according to the requirements of the design drawings, indicate the design changes, the positions of reserved holes and structural columns, the specific methods of lintels, the types of masonry materials and the strength grades of mortar, etc. in the detailed drawing of each house type, and prepare a special construction scheme for masonry, which shall be approved by the supervisor. Detailed technical disclosure shall be made to the team according to the approved scheme, and submitted to the supervisor for filing at the same time. 2.2 Submit the secondary structure construction setting out (including elevation line), toilet and bathroom plain concrete sill base treatment, tie bar, structural column, cast-in-place lintel, portal jamb reinforcement and formwork to the supervisor in sections and layers for concealed acceptance. In case of self concealed construction without acceptance, the quantities shall not be confirmed.