Construction copy of 20m prestressed hollow slab beam
This project is located in xx Town, xx City, which is a key project of xx Province - xxxxxx Ecological Leisure Project. It is one of the main channels for the external traffic of xx Ecological Leisure Zone. The starting point is located in Xiaxi District, Xiawu Village, connecting Xiang'an South Road. The route runs from west to east, parallel to the provincial highway 201, passing through xx Village, xx Village, xx Village, and xx Village, and ending at xx Village, connecting Nangang Road. The total length of the route is 9.387km. A total of 3 medium bridges of 198.36m are set along the whole line in this design. See the following table for details of bridge settings: Table 2-1 No. Bridge Center Pile No. River name and bridge name Full width of bridge deck (m) Total length of bridge (m) Bridge intersection angle (degree) Number of holes and aperture (hole-m) Upper structure pier, foundation abutment and foundation 1 K3+568.2 Xidongxi Middle Bridge Left: 29.5 Right: 26.0 66.12 60 3 × 20 precast prestressed concrete simply supported hollow slab cylindrical pier, pile foundation ribbed slab abutment Pile foundation 2 K6+514.2 Laogangxi Medium Bridge 2 × 22.5 66.12 60 3 × 20 precast prestressed concrete simply supported hollow slab cylindrical pier, pile foundation pile column platform, pile foundation 3 K7+845.0 Xibanxi Medium Bridge 2 × 22.5 66.12 120 3 × 20 precast prestressed concrete simply supported hollow slab cylindrical pier, pile foundation pile column platform, and pile foundation The superstructure of the three medium bridges is prestressed reinforced concrete simply supported hollow slab beam, Simply supported structure, continuous deck. The three medium bridges are located on the transition curve, circular curve and straight line respectively, and the curve radius is large. In order to facilitate the construction of precast hollow slab beams, the layout method of replacing curve with straight slab is adopted. The specific layout is as follows: (1) Xidongxi Medium Bridge: the precast slab beam is 0.95m high, and the post tensioning process is adopted, in which the left width is 29.5m, 23 precast slabs are arranged in a single span, the right width is 26.0m, and 20 precast slabs are arranged in a single span. The whole bridge has 129 prefabricated hollow slabs in total, including 12 side slabs and 117 middle slabs. The cantilever length of prefabricated side slabs is 505mm and 630mm respectively, the width of middle slabs is 1.24m, and the width of installation joints is 0.01m; (2) Laogangxi Medium Bridge: the full width of a single bridge is 22.5m, and 18 precast hollow slabs are arranged horizontally in a single span. The whole bridge has 108 prefabricated hollow slabs in total, including 12 side slabs and 96 middle slabs. The cantilever length of the prefabricated side slab is 255mm, the width of the middle slab is 1.24m, the width of the installation joint is 0.01m, and the height of the prefabricated beam is 0.95m. The post tensioning process is adopted; (3) Xibanxi Medium Bridge: the precast beam is 0.95m high, and the post tensioning process is adopted. The width of a single bridge is 22.5m, and 17 precast hollow slabs are arranged in a single span. The whole bridge has 102 prefabricated hollow slabs in total, including 12 side slabs and 90 middle slabs. The cantilever length of prefabricated side slabs is 630mm, the width of prefabricated middle slabs is 1.24m, and the width of installation joints is 0.01m.