Scaffolding Disclosure of safety technical measures for demolition
1、 Scaffold erection and dismantling personnel must be professional scaffolders who have been assessed and work with certificates. Wall connecting members can be removed only after all detachable members on them are removed. 2、 Before dismantling the scaffold, comprehensively check the scaffold to be dismantled, draw up the operation plan according to the inspection results, submit it for approval, and prepare the work after technical disclosure. 3、 Before dismantling the scaffold, it is necessary to check the construction site environment, including overhead lines, external scaffolding, ground facilities and other obstacles, ground anchors, guy ropes, wall connecting rods, and the lifting points, accessories, and electrical devices of the dismantled scaffold. Those that can be removed in advance should be removed as far as possible. 4、 During demolition, the operation area shall be marked out, and ropes and fences or warning signs shall be set up around the area. The ground shall be surrounded by specially assigned personnel, and non operators shall not be allowed to enter. 5、 During demolition, unified command, up and down coordination and action coordination must be carried out. When unfastening fasteners related to another person, the other person must be informed and allowed to prevent falling and hurting people. 6、 It is not allowed to change people in the middle of the removal. If it is necessary to change people, they should explain the removal clearly before leaving 7 No hidden danger parts shall be left when the scaffold is dismantled every day. 7、 It is strictly prohibited to collide the power line near the scaffold when dismantling the scaffold to prevent electric shock accidents. 8、 During the removal process, all the loose rods and accessories shall be removed and transported away in time to avoid supporting and leaning against the loose rods by mistake. It is strictly prohibited to throw down the removed rods and accessories, and they should be hoisted to the ground. At the same time, coordination work should be done. It is prohibited to carry out dangerous operations such as removing heavy rods and accessories by one person. 9、 All rods and fasteners shall be separated during removal, and fasteners shall not be attached to rods or sent to the ground with two rods connected. 10、 All scaffold boards shall be handled vertically from outside to inside to prevent scaffold boards and garbage from falling from high places to hurt people. 11、 The dismantled spare parts shall be put into the container and lifted down with a basket; The removed steel pipes shall be bound firmly and lifted at two points. Throwing from high altitude is strictly prohibited. 12、 When the wind level is above six (including six), the scaffold removal construction shall be stopped.