[Hefei] Anti floating anchor rod construction of frame shear structure apartment building programme
This project includes 27 floors of 1 # 2 # building, with a building height of 81.9m; Building 3 # 4 # has 31 floors, with a building height of 93.9m; 1 commercial building, 1 underground garage and 1 property management room. The total construction area is 109840 ㎡, and the basement construction area is 23531 ㎡. The underground garage adopts lower column pier+slab raft foundation, 1 # building adopts prestressed high-strength concrete pipe piles, 2 # 3 # 4 # building adopts slab raft foundation (CFG pile composite foundation), and commercial building adopts raft+lower column pier foundation+anti floating anchor rod. The pure basement outside the main building is a frame structure; The 1-5 floors of 1 # 2 # building are frame shear wall structures, the wall columns from the 6th floor to the 25th floor are fabricated shear wall structures, the 26 floors to the roof are frame shear wall structures, the 1-5 floors of 3 # 4 # building are frame shear wall structures, the wall columns from the 6th floor to the 28th floor are fabricated shear wall structures, and the 28 floors to the roof are frame shear wall structures. The total number of anti floating anchor bolts is 180, of which the total length of anchor bolts is not less than 12 meters, and the length of anchor ③ layer soil is 12 meters. Anchor hole diameter ≥ 200mm. The grouting body is made of cement mortar (mixed with micro expansion agent accounting for about 10% of the cement consumption) with a strength of M30. Before grouting, the anchor bolt hole should be cleaned. Three three-stage hot-rolled steel bars with a diameter of 25mm are used for spot welding. The anchor rod positioning bracket is made of three-stage hot-rolled steel bars with a diameter of 18mm, and the spacing is not more than 1.5m. The fixed steel bars are three-stage hot-rolled steel bars with a diameter of 25mm, and a section of 50mm is added every 1.5m, which is firmly welded with three longitudinal bars. The length of anchor bolt body anchored into the bottom plate shall not be less than 40d. The anchor bolt shall be derusted, and the thickness of mortar protective layer shall not be less than 35mm. The deviation of anchor bolt shall not be greater than 5%.