Temporary power construction of a bridge project programme
The main power supply of the external line project is provided by Party A, and it is laid in a pipe. The line should use the TN-S system three-phase five wire system, and each branch line should be erected with lines and five core cables. The lighting power in all offices should be 220V, the lighting power in the shed should be 36V, and the empty frame should use a wooden 8m pole. The pole distance should be determined according to the actual situation. The site leveling road is unobstructed, providing a good working environment for the construction. All kinds of materials and tools are complete, and the transportation is convenient, which can ensure the timely supply of materials, sufficient construction personnel, mature technical conditions, and full coordination with the work of Party A, which is conducive to the development of the work. According to the civil construction drawings, and combined with the site conditions, the site of steel bars, wood formwork and other electrical facilities has been determined, and the site construction regulations are good. This information is 9 pages in total.