A sound system has been established according to IS09001;2000, IS014001, and GB/T28001 have set clear goals, fully mobilized professional and technical personnel, established a perfect construction organization, and participated in the early bidding of the project.
Interior decoration organization design scheme of an office building in Zhejiang - Figure 1
Special statement: This material belongs to the sharing uploaded by usersDownloaded content, only for learning, not for commercial use. If there is any copyright problem, please timelycontactStation delete!
Materials required for this project must be sampled, compared, qualified and priced together with the Owner, the Supervisor and the Designer according to the requirements of design and construction specifications before purchase, and can only be purchased after being approved and approved in writing by the Owner.
We will cherish this precious opportunity and actively participate in this qualification with full sincerity, enthusiasm and the spirit of serving the owner;It is an honest decoration enterprise in Ningbo and one of the top ten decoration brand enterprises in Ningbo;Member of China Interior Decoration Association;Member of Zhejiang Decoration Association;Executive director unit of Ningbo Interior Decoration Association;Won the Excellent Architectural Decoration Engineering Award of Zhejiang Province in 2005;Won the 2005 Ningbo Excellent Architectural Decoration Engineering Award;Won the Excellent Decoration Design Award of Zhejiang Province in 2005;Won the 2005 National Demonstration Project Award;Won the Silver Award of "Asbestic" Cup Home Creativity;"Xinguang lacquer" cup furniture creative bronze award.The company has been established for more than ten years
Brush a layer of plain cement slurry, and use 1:0.2:2 cement lime paste mortar as the bonding layer, with a thickness of 1.2cm. After the bottom is plastered, the waterproof of the waterproof wall of the toilet wall must be completely dry. After it is completely dry, use the interface agent and plain cement to spray slurry on the waterproof layer. After the mortar is completely solidified on the wall, the inlay can be carried out.When tiling, a layer of interfacial agent shall be brushed along with the tiling.
The traffic of this project is convenient, but limited to the requirements of Beijing Traffic Management Bureau for the traffic control period in this area, large and medium-sized vehicles transporting materials cannot enter this area from 6:00 a.m. to 22:00 p.m., which increases the difficulty of material transportation and garbage removal during the construction of this project.
The company is a limited liability company mainly engaged in architectural decoration, which was established in November 1993.The company is mainly engaged in architectural decoration engineering design and construction business.Since its establishment, the company has developed the market, bravely explored, and achieved good results. It is a Class II qualification for building decoration construction and a special qualification for building decoration design;It is an honest decoration enterprise in Ningbo and one of the top ten decoration brand enterprises in Ningbo;Member of China Interior Decoration Association;Member of Zhejiang Decoration Association;Executive director unit of Ningbo Interior Decoration Association;Won the Excellent Architectural Decoration Engineering Award of Zhejiang Province in 2005;Won the 2005 Ningbo Excellent Architectural Decoration Engineering Award;Won the Excellent Decoration Design Award of Zhejiang Province in 2005;Won the 2005 National Demonstration Project Award;Won the Silver Award of "Asbestic" Cup Home Creativity;"Xinguang lacquer" cup furniture creative bronze award.Since its establishment for more than ten years, the company has taken honesty as the foundation and quality as the life of the enterprise, won the recognition and praise of the majority of owners, and become a well-known brand enterprise in the building decoration industry of our city.
First of all, I would like to thank the owner for giving our company the opportunity to participate in the decoration construction bidding of this project. I am not very honored. Our company will certainly cherish this precious opportunity and actively participate in the bidding of this project with full sincerity, enthusiasm and the spirit of serving the owner.
Establish the quality assurance system of the project, implement quality management, establish an all-round management of organizational structure, responsibilities, procedures, processes and resources, and integrate the production factors of the project, such as people, finance and materials, according to various work standards, management standards, technical standards, etc.
With the development of social economy and the progress of building technology, the construction process of modern architectural decoration has become a very complex production activity.The architectural decoration construction of a large construction project not only includes organizing hundreds of various architectural decoration technical workers and a large number of various architectural decoration machinery and equipment into the project construction in an orderly manner, but also includes organizing a wide range of architectural decoration materials
With the development of social economy and the progress of architectural technology, the construction process of modern architectural decoration has become a very complex production activity.The architectural decoration construction of a large construction project not only includes organizing hundreds of various architectural decoration technical workers and a large number of various architectural decoration machinery and equipment to be put into the project construction in an orderly manner, but also includes organizing the production, transportation, storage and supply of a wide range of architectural decoration materials, products and components;Organize the supply, repair and maintenance of construction equipment;Organize temporary water supply, power supply and heat supply on the construction site, and arrange various temporary facilities required for production and life on the construction site.The organization and coordination of these works is of great significance for the construction of the project in a fast, good and economical manner.
The civil engineering department of the project is under construction, and the construction site is large. Now it basically has the conditions for the second decoration construction. The temporary water supply and power supply are provided by Party A, which can meet the construction requirements.
1、 Project overview The office building of the Party Working Committee of the * * Town Community is located in the "* *" Phase III Complex Building in * * Town, Ningbo City, Zhejiang Province, which has two floors, with a total construction area of 1700 m2. The contracting method: contracting for labor and materials, and the scope of contracting: all projects except finished furniture, potted plants, air conditioners and other equipment.Acceptance criteria for project quality: the project shall be accepted according to the construction drawings, practice descriptions, design changes, and the Code for Acceptance of Quality of Building Decoration Engineering (GB50210-2001).
The total construction area is 1700 m2. Contracting method: contracting for labor and materials. Contracting scope: all works except finished furniture, potted plants, air conditioners and other equipment.Acceptance criteria for project quality: the project shall be accepted according to the construction drawings, practice descriptions, design changes, and the Code for Acceptance of Quality of Building Decoration Engineering (GB50210-2001).
1、 Project overview The office building of ×× city is located at. City ×× Road.It is composed of one main building and two auxiliary buildings. There are 1 floor underground, 17 floors above the ground, 69.3 meters high, 2 floors above the ground and 1 floor underground for the east and west auxiliary buildings.ByThe municipal architectural design and research institute is responsible for the main design;××××× Co., Ltd. has the honor to undertake the in-depth design, material procurement, processing, manufacturing, installation and warranty of the curtain wall project of ××××××× government office building in ×× city.The total construction area of the office building in ×× city is 38787 square meters;The building form is rectangular, and the facade has no major change, but the forms are diverse. The curtain wall of the exterior wall is mainly composed of aluminum alloy portal window, granite curtain wall and aluminum plate curtain wall, and there are other decorations such as metal railings.
The interior decoration construction organization design scheme of an office building is detailed and rich, with accurate and comprehensive design, which can be downloaded by netizens.
****The decoration of the office of the insurance company ************ is the second decoration project of the office building built by the Shenzhen Branch of * * * * Insurance Company.The project is located in Building 24, ****** Street, Shenzhen, with a building area of 150m2, and is used for office work.The funds for the project have been confirmed. The design drawings for the construction phase have been completed by * * Decoration Engineering Company. Temporary water and electricity, water and roads have been connected to the site. The preparatory work for the construction phase is ready and meets the construction conditions for mobilization.The technical characteristics of this project are: the engineering design is of high grade, the selection of engineering materials is strictly required, and high-grade domestic materials and imported products are mostly used, mainly including high-grade floor tiles, Seagull high-grade interior wall paint, cherry wood veneer, Matsumoto Songke Electric, and Wangxin brand mineral wool board ceiling.
First of all, I would like to thank the owner for giving our company the opportunity to participate in the decoration construction bidding of this project. I am not very honored. Our company will certainly cherish this precious opportunity and actively participate in the bidding of this project with full sincerity, enthusiasm and the spirit of serving the owner.
Construction organization design is a subject that aims at the complexity of engineering construction and studies the objective laws of overall arrangement and systematic management of engineering construction.It studies how to organize and plan the whole construction of a proposed project, and seeks the most reasonable organization and method.
The final decoration of the project is the function of setting off and beautifying, and other specialties are the embodiment of functional effects;Therefore, in the decoration construction, coordination with the above professional construction units should be the key to the success of the project construction.
The office building of the Party Working Committee of a community in a town is located in the "* *" Phase III Complex Building in * * Town, Ningbo City, Zhejiang Province, which has two floors, with a total construction area of 1700 m2. The contracting method is to contract labor and materials, and the contracting scope is to complete all works except finished furniture, plant potted plants, air conditioners and other equipment.
**The office building of the Town Community Party Working Committee is located in the "* *" Phase III Complex Building in * * Town, Ningbo City, Zhejiang Province, which has two floors and a total floor area of 1700m2.
The total construction area of the project is 25411 ㎡, with nine floors above the ground (partial ten floors) and two floors underground;Structural form: frame shear wall structure;Main body capping;The installation of aluminum curtain wall and stone curtain wall panels is expected to be completed by the end of June;The interior rough decoration is completed;The peripheral doors and windows are closed.The main decorative style is modern Chinese decorative design style.
According to the construction drawings and budget, determine the main material samples with Party A, the design unit and the supervision unit, and seal the samples;Prepare material demand plan, implement qualified suppliers, and organize supply;Prepare transportation plan and scheme;Determine the type and quantity of construction machinery.
As one of the construction companies lucky to participate in the bidding quotation of the decoration project, our company is determined to carefully prepare the bidding documents in strict accordance with the requirements of the bidding documents, actively respond to the provisions of the bidding documents, and take practical actions to successfully complete the bidding work and win the bid.
In order to strengthen the leadership of the project construction, the Project Department has the following engineering management levels: Design Department, Administration Department, Engineering Department, Materials Department, Quality Safety Department, Finance Department, etc.According to the characteristics of the project, the management level below the project general manager is the operation implementation level.
This information is the construction organization design scheme for the decoration of an office building, which is detailed and can be used for reference.
The civil engineering department of the project is under construction, and the construction site is large. Now it basically has the conditions for the second decoration construction. The temporary water supply and power supply are provided by Party A, which can meet the construction requirements.The carpets of this project include floor color separation square carpets, oval computer carved carpets, etc. The paved parts include halls, stairways and walkways.The laying construction is divided into fixed laying and movable laying.The fixed laying construction is detailed here, and the movable laying is briefly described.
The civil engineering department of the project is under construction, and the construction site is large. Now it basically has the conditions for the second decoration construction. The temporary water supply and power supply are provided by Party A, which can meet the construction requirements.
According to the relevant requirements of the project contracting, in order to ensure the smooth construction and progress of the project, the technical documents of the drawings shall be further checked before the commencement of the work, and the joint review shall be carried out
When hanging stones, lay them one by one according to the benchmark control line, and limit the hanging height within 1.5M every day to prevent uneven settlement, deformation and uneven seam
This information is the decoration construction organization design of an office building in Hebei. The content of the information is clear and can be used for reference. Welcome to download.
The civil engineering department of the project is under construction, and the construction site is large. Now it basically has the conditions for the second decoration construction. The temporary water supply and power supply are provided by Party A, which can meet the construction requirements
The civil engineering department of the project is under construction, and the construction site is large. Now it basically has the conditions for the second decoration construction. The temporary water supply and power supply are provided by Party A, which can meet the construction requirements.
The central molding part of the ceiling in this project is the ceiling that can be accessed for maintenance, so the bearing capacity of local concentrated load must be considered, including dead load and moving load.The suspender must be made of angle steel or round steel.
This document is a design scheme for decoration construction organization in an office complex building, which is detailed and can be used for reference.
The construction organization design is applicable to.The construction organization design is prepared based on: 1. Construction bidding documents.2. Interior decoration drawings provided by Hebei Architectural Design Institute.3. National standards: Code for Construction Acceptance of Building Decoration Engineering, Code for Advanced Decoration Engineering, Code for Fire Protection of Building Decoration Engineering, 4. ISO9000 international quality standard related documents.5. Decoration construction experience and data