Construction scheme for maintenance and reconstruction of an office building
1. The site layout plan is intended to make the following arrangements for the mechanical equipment and construction site required by the project in order to comprehensively control materials, machinery, manpower and management. (1) During the construction of construction roads, the existing hardened roads shall be used according to the specific conditions of the construction site. At the same time, the fire ring road around the building will be opened to assist the transportation of various materials. The construction site will be fully closed. (2) The stacking of materials shall be based on the needs of materials between the construction site areas, and the stacking room of finished materials shall be set up between each area; Semi finished material stacking room; Fabrication material stacking room; Stacking room for combustible materials; Stacking room for various hardware accessories; Glass products stacking room; Sanitary ware stacking room, etc. (3) The construction machinery shall be equipped with enough construction machinery and accessories required by construction machinery according to the needs of the construction site. The machinery required on the construction site includes: air compressor, electric saw, impact drill, electric hammer drill, cutting machine, portable planer, pressure planer, nail gun, mill, nail gun, etc. (4) The vertical and horizontal transportation of materials shall be equipped with enough decorative materials according to the construction area divided by the construction site. The materials must be controlled in parallel and allocated evenly between the areas. The horizontal transportation of materials shall be mainly carried by trucks or a small part of materials shall be transported by miscellaneous workers; The vertical transportation of materials is mainly carried out by miscellaneous workers. In order to ensure the construction progress, sufficient porters must be allocated according to the construction progress. (5) Set up a finished product processing yard outside the construction site In order to reduce the cross operation on the construction site, our construction unit has decided to set up an on-site finished product processing workshop outdoors (the specific location is approved by the owner) to speed up the construction progress, shorten the working hours of cross construction, ensure the construction progress and ensure the construction quality.