This document is the management measures and commitments for finished product protection and project warranty, including: finished product protection management: the project is large in volume and complex in structure, so many processes must be inserted in advance to ensure the construction period.And cross operation will be carried out with the construction of main works.Therefore, during the construction of the project, some subdivisional and divisional works may be completed in advance. If the next process does not pay attention to the constructed finished products or take proper measures to protect them, the existing finished products will be damaged or destroyed, affecting the project quality.This will not only increase the repair workload, waste materials and delay the construction period;What is more serious is that some damages are difficult to restore to the original state and become permanent defects.Therefore, the protection of finished products is an important link related to ensuring project quality, reducing project cost and completing on schedule.For this reason, we will do a good job in finished product protection.
Uploader:Upload time:2019-12-13 10:24:16Document format:docxNumber of collections:zerothe number of pages:twenty-twoComments:zero
Management measures and commitments for finished product protection and project warranty - Figure 1
Special statement: This material belongs to the sharing uploaded by usersDownloaded content, only for learning, not for commercial use. If there is any copyright problem, please timelycontactStation delete!
For processing and ordering, such as aluminum alloy products, joinery products, lamps, distribution cabinets and other materials, the factory must have reliable packaging and protection measures
The project is located in the Economic Development Zone of XX City, bordering Pearl Avenue in the east and the office compound of the Municipal Party Committee, the People's Congress and the CPPCC in the south, with a total construction area of about 65000m2. There are 27 towers on the ground and 1 basement underground.The tower building is 98.8m high (from outdoor terrace to structural roof slab), and the podium building is 20.4m high (from outdoor terrace to parapet top).The tower structure type is frame core tube structure, and the podium structure type is frame structure.
During the construction, ensure that the finished products are not damaged, such as the corners, flatness and surface finish of the pool body;The building decoration is intact as before;No leakage or blockage of pipeline;The equipment is free from abrasion and operates normally
Establish a special management organization for finished product protection, coordinate the concerted action of all units, and carry out alternate operations in a disciplined and orderly manner, so as to ensure that the raw materials, finished products, semi-finished products, process products used for construction and the completed divisional and sub divisional works are effectively protected, and ensure the construction quality of the whole project.
Through analyzing the current situation and existing problems of project cost management in China, this paper proposes to carry out reform from strengthening the information work of project cost, doing a good job in bidding management, and standardizing and training the intermediary service agencies of project cost consultation, so as to meet the needs of the rapid development of modern society and economy.
This article is the detailed rules for the implementation of protection measures for finished decoration products, which is full of details and can be used as a reference for the vast number of netizens.
The materials used for dismantling and erecting scaffolds and springboards shall have corresponding protective measures for aluminum frames, otherwise, it is not allowed to drag on the door and window frames, install pipelines, and prevent the equipment from damaging the curtain wall.It is not allowed to hit, nail or scratch on the curtain wall and window frame. After the installation of curtain wall and window glass, the sign of "Caution glass" shall be pasted immediately.
The installation of panel, module, distribution frame, cabinet, control box, control cabinet, camera and alarm shall be carried out after the completion of internal installation.Other installation shall be carried out in coordination with relevant procedures
Prefabricated pipes shall be arranged by item according to the number and installed with wooden blocks, and shall not be placed horizontally in double layers.It is not allowed to stack large pipes with small ones, and foot pedal and objects shall be prevented from hitting.
As a basic industry in the national economy, the power system bears an important historical mission and social responsibility in energy conservation and emission reduction.The following article discusses the effective measures for energy conservation and emission reduction in power system.
Establish a special management organization for finished product protection, coordinate the concerted action of all units, and carry out alternate operations in a disciplined and orderly manner, so as to ensure that the raw materials, finished products, semi-finished products, process products used for construction and the completed divisional and sub divisional works are effectively protected, and ensure the construction quality of the whole project.
With the influence of social progress and economic development, modern large-scale projects and high-rise buildings have sprung up like mushrooms. The development and application of water supply and drainage in high-rise buildings have also made breakthrough progress.However, in the construction process of large building projects, people often pay attention to the water supply and drainage function of the building to be built, and often ignore the temporary water management during the construction process.This paper tries to clarify the relationship between temporary construction water, finished product protection and safety management from the concept of temporary construction water, and the matters that should be paid attention to in the project management of temporary water supply and drainage.We will discuss with you how to define the scope of responsibility of all parties involved in the construction of temporary construction water, the responsibilities of relevant project management personnel, and how to standardize the management of construction water in the protection of finished products, so as to properly prevent the loss of construction water and prevent the occurrence of safety accidents related to temporary construction water.
When the waterproof sealant is embedded around the wall and window frame, the operation should be careful and should not pollute the curtain wall and window frame
Stairs shall be constructed separately. First, one stair shall be closed, and then another stair shall be constructed one week after the construction. After the construction of the stair tread surface, the angle protection plate must be made with plywood or bamboo plywood before walking to protect the stair corner from being damaged
Strengthen the relationship between the General Contractor and the Subcontractor, dispute and interfere with each other, and report to the supervision company if the finished products are damaged due to mutual influence
When installing the outer wall waterproof sleeve, the sleeve must be bound with the reinforcement and welded firmly to avoid displacement. When adjusting the reinforcement in civil engineering, it must be adjusted at any time. During the concrete pouring process, there must be a special person to coordinate the calibration and watch over the mold and embedded parts to avoid displacement;
The scheme is reasonably arranged, with complete chapters, rich content, complete format, neat and beautiful content layout, smooth sentences, smooth expression of the full text, and can be used directly
This document is the detailed document of the plan of finished product protection measures in a region. The content of the document includes the scope of finished product protection. The document conforms to the standard and is available for reference.
The general construction contractor shall establish a finished product protection organization, and the specialized subcontractors shall appoint full-time personnel to join the finished product protection organization. The finished product protection organization shall coordinate the consistent actions of the specialized construction parties, and conduct the interpenetrating operations in a disciplined and orderly manner.In the process, focus on the protection of finished products in the construction of each discipline, ensure that the raw materials, finished products, semi-finished products, process products and completed sub divisional products used for the construction of each discipline are effectively protected, and check at all levels before, during, after, before and during the completion and delivery process to ensure the construction quality of the whole project.
This document is a reflection on the bidding work of ship building projects. In order to establish the image and brand of Jiangsu Channel, leaders of Jiangsu Channel Bureau have been forward-looking since 2002. After the separation of enterprises and enterprises in the channel system, the equipment investment is focused on the construction of boats. It clearly points out that the goal of new type boats should be "first-class in the province and leading in the country".The content is detailed and worth downloading.
This document is about some views on strengthening the management of project cost in our province. Project cost management is a reasonable determination and effective control of project construction investment, an extension and expansion of budget estimate quota management, and a project cost management discipline that adapts to the combination of planned economy and market regulation.The content is detailed and worth downloading.
When installing the outer wall waterproof sleeve, the sleeve must be bound with the reinforcement and welded firmly to avoid displacement. When adjusting the reinforcement in civil engineering, it must be adjusted at any time. In the process of pouring concrete, a special person must be assigned to coordinate the calibration and watch over the mold and embedded parts to avoid displacement
The Ministry of Infrastructure of the State Grid requires that all new substations built after 2011 should be built in accordance with intelligent substations. A new problem lies in front of the integrated automation team. What method should the team adopt for equipment inspection and device weekly calibration? This paper introduces the difference between traditional substations and intelligent substations, as well as the test method for relay protection in intelligent substations.
This document is the construction environmental management and protection measures of a construction project, and the construction environmental management and protection measures have been formulated to prevent noise, dust, sewage, light pollution, garbage and other pollution.
Drawing isoline and profile map is a common problem in hydrological research.Taking the sulfate data of groundwater quality as an example, this paper introduces the basic methods and steps of drawing contour map and profile map with Surfer9, and briefly compares and analyzes the advantages and disadvantages of several commonly used spatial interpolation methods in the software.
Based on the way of metal halide lamp and supporting work, and with in-depth rational analysis as evidence, this article extensively and profoundly expounds the colorful reality of metal halide lamp products and supporting work that are currently in the leading position in China.In order to further improve the overall level of metal halide lamp lighting, strengthen the norms and constraints, promote exchanges and cooperation, and follow the best practices and strive for perfection to eliminate the reality and impact of the separation of forces in the field of metal halide lamp lighting as soon as possible.
The electric non pressure air door controller is mainly used in each connecting lane between the air inlet and return lanes and the main air inlet and return lanes in the coal mine. The non pressure air door is an updated product of the air door currently used.There are full transparent and ordinary pressure free dampers.The specifications and varieties of non pressure damper can be customized according to the required size.
This document is a detailed document of protection measures for finished and semi-finished products in a certain area. The content of the document includes: safety construction organization description, acceptance standards, technical standards and other forms. The document conforms to the standards, has reliable data, rich content, and detailed ideas, which can be used for reference
Protective measures such as protective shed, warning board and on-site patrol by specially assigned person shall be taken, and corresponding protective measures shall be taken for key parts of some equipment, such as adding lubricant.
When transporting materials and equipment, be careful not to damage the glass curtain wall due to collision;Projects constructed within the scope of glass curtain wall shall be closely coordinated with civil engineering and decoration, and shall be completed before the construction of glass curtain wall as far as possible;Inevitably, the construction projects (such as additional projects) that need to be installed after the installation of the glass curtain wall should be isolated and protected by erecting galvanized steel plates, so as not to damage the glass curtain wall.