The hotel was built in a city in the south of China. It consists of a tower, a podium and an annexArchitectureIt is composed of buildings with a total area of nearly 30000m2, buildings with a total area of 4850m3 and a building area of 4864m2, of which the main building is 4514m2. The tower has 37 floors, a total height of 108m, 804 guest rooms and 10 elevators.The podium is 2-3 floors, and the non-standard floors of the podium and tower are public places.The hotel has a large amount of decoration works and high technical requirements, most of which are concentrated on the lower two floors.The interior decoration works include latex paint, wallpaper, marble, mosaic, plastic asbestos brick, ceramic tile and crock tile, etc;The outdoor decoration works are all glass mosaics.
Hotel decoration project construction organization design scheme (30 pages in total) - Figure 1
Special statement: This material belongs to the sharing uploaded by usersDownloaded content, only for learning, not for commercial use. If there is any copyright problem, please timelycontactStation delete!
This information is the construction organization design scheme for the fine decoration project of a hotel in a certain area. The content is detailed and can be used for reference.
Before the equipment and materials used for the installation of the project enter the construction site, put forward the electrical material plan, and indicate the relevant provisions and requirements of the materials required for the project in the plan;When materials enter the construction site, especially those related to safety, the quality of materials must be jointly inspected by the relevant personnel of the Quality Inspection Department, the Material Department of the company, the engineering technology director, and the installation director, and at the same time, whether there are exit certificates, manufacturers, and quality assurance certificates.If the mobilized materials are qualified and the three certificates are complete, they can enter the construction site, and can only be installed and used after submitting the material mobilization inspection application form to the supervising engineer for approval.Material quality can be rejected by one vote.
Decoration engineering construction organization design Decoration engineering construction organization design Decoration engineering construction organization design Decoration engineering construction organization design Decoration engineering construction organization design Decoration engineering construction organization design Decoration engineering construction organization design Decoration engineering construction organization design Decoration engineering construction organization design Decoration engineering construction organization design Decoration engineering construction organization design Decoration engineering construction organization design
4.3.1 Design according to the outer eaves drawing to ensure that the outer eaves are pasted symmetrically and beautifully like mushroom stones, accurately calculate and adjust the gap t, and the paint spray block is uniform, three-dimensional, and ensure the effect.4.3.2 Sample making: before the structure is accepted, select the site enclosure or the external wall of the office to carry out the construction of the outer edge decoration sample, and apply soil to solve the uniformity of the coating block and the A-body feeling, so as to reach the pre controlled quality standard.For interior decoration, select representative rooms for sample construction, including: fine stone wave floor sample, kitchen, bathroom wall, floor tile sample, and sample room on the second floor above the ground.Large area construction will be carried out after self inspection by all disciplines of the company, acceptance by the supervisor and the owner.4.3.3 Water, electricity and civil engineering circle review: in order to avoid the rework of the project caused by the wood circle between disciplines, before decoration, the chief engineer of the company and all professionals of the project shall participate in the circle review of the discipline, and all equipment, holes, devices, etc. in the same position shall be drawn on a drawing by computer. If there is no circle, it shall be solved in advance before decoration.
3.2.1 Polystyrene board, DBI mortar, DEA mortar, DTA mortar, jointing agent, galvanized steel wire mesh, alkali resistant glass fiber gridding cloth shall be provided with factory certificate, test report and retest report, and can be used only after being qualified.3.2.2 Face brick: The surface of face brick shall be smooth, square, flat and solid, and its variety, specification, size, color and pattern shall be uniform.There shall be no defects such as missing edge, corner, dark mark and crack.After mobilization, the size, surface quality, water absorption and frost resistance of face tiles shall be re inspected, and they can be used only after being qualified.3.2.3 The face brick binder DTA and coating shall be provided with factory certificate, test report and retest.
Before the construction of the project, each room on each floor shall be provided with a unified elevation line and cross center line for civil decoration and professional facilities installation. Therefore, at the beginning of the decoration project, the wall of each room shall be snapped with a elevation line of 0.5m, which is similar to the structural stage. The cross center line shall be snapped on the floor, ceiling and wall, and the cross line shall be consistent with the bottom.
This material is the hotel project construction organization design scheme, which is detailed and practical. Welcome to download it for reference.The hotel was built in a city in the south of China. It consists of towers, podiums and ancillary buildings. It covers a total area of nearly 30000m2. The buildings cover an area of 4850m3, with a building area of 4864m2, of which the main building is 4514m2. The tower has 37 floors, a total height of 108m, 804 guest rooms and 10 elevators.The podium is 2-3 floors, and the non-standard floors of the podium and tower are public places.
The hotel was built in a city in the south of China. It consists of towers, podiums and ancillary buildings. It covers a total area of nearly 30000m2. The buildings cover an area of 4850m3, with a building area of 4864m2, of which the main building is 4514m2. The tower has 37 floors, a total height of 108m, 804 guest rooms and 10 elevators.The podium is 2-3 floors, and the non-standard floors of the podium and tower are public places.
The tower is a cast-in-place reinforced concrete frame tube structure, which is composed of a square central tube with a net size of 12.5m × 12.5m, 24 inner columns, 20 outer columns and floor slabs;There are 2.97m × 2.97m cast-in-place reinforced concrete corner cylinders at the four corners of the tower;13 cm thick reinforced concrete slab for the standard floor of the tower.
Make sample: before the structure is accepted, select the site enclosure or office exterior wall to carry out the construction of exterior decoration sample, and apply soil to solve the uniformity and A-body feeling of the coating block, so as to reach the pre controlled quality standard.For interior decoration, select representative rooms for sample construction, including: fine stone wave floor sample, kitchen, bathroom wall, floor tile sample, and sample room on the second floor above the ground.Large area construction will be carried out after self inspection by all disciplines of the company, acceptance by the supervisor and the owner.
This document is a model of construction organization design scheme for the fine decoration project of a high-rise hotel. The contents include: project overview and preparation basis, construction deployment, main construction scheme and construction technology, labor plan, use plan of main construction machinery, consumption plan of main equipment and materials, components, etc. The contents are detailed and can be used for reference.
Demolition works, interior decoration works, water supply and drainage works, electrical installation works, etc. of standard guest rooms on the 17th floor, administrative clubs, public elevator halls and walkways, business suites, presidential suites, public elevator halls and walkways on the 18th floor of a hotel.It does not include carpet engineering, fire engineering, curtain fabric, movable furniture, etc.
Construction organization design scheme of a hotel interior fine decoration project in jinan, shandong construction organization design scheme of a hotel interior fine decoration project in jinan, shandong
According to the general construction schedule issued by the general contractor, a new construction schedule for fine decoration will be prepared, and the monthly schedule of fine decoration system for the next month will be submitted before the end of each month to monitor the construction progress
The decoration materials of this project are of medium grade, so the quality of materials, especially the consistency of specifications, dimensions and colors, is difficult to control.The quality objective of this project is the "Great Wall Cup" project. At present, the control of structure size and appearance has reached the pre control objective. Therefore, the construction difficulty caused by the materials themselves must be overcome for the quality of the decoration project to achieve the "coarse grain and fine workmanship" and ensure that the appearance and actual measurement reach the quality pre control goal.
The construction organization design is G76-AThe interior decoration project of the school project on the plot is specially prepared, which involves relevant project overview, schedule, construction scheme, management personnel organization, quality assurance system, safe and civilized construction, finished product protection, etc. It is hoped that all relevant units will clarify the design and construction points of the interior decoration project, closely cooperate in the construction process, and complete the construction tasks on schedule with quality and quantity guaranteed.
The structural form of the project is frame structure, with 6 floors above ground and 1 floor underground.The construction project includes building and plastering of enclosure wall, light steel keel gypsum board ceiling, floor tile floor, doors and windows, painting, wood paint, curtain wall, etc.
This project includes two sections, namely, Ningbo Customs' roof repair and the repair of the interior and exterior walls of the dormitory in Lane 48, Liuzhuang Street (the roof repair project of Ningbo Customs will be constructed immediately after the signing of the contract, and the repair of the interior and exterior walls of the dormitory in Lane 48, Liuzhuang Street will be constructed after the completion of the renovation of the water works.)
This data is the construction organization design scheme of decoration project of a bid section in ShenzhenThe content is detailed and can be used for reference.
The production command and dispatching, technical quality and safety are our company's full-fledged agents stationed in the decoration construction project. They are responsible for the management and service of the operation layer to ensure that the quality and duration of the project meet the requirements of the owner.
The construction area of the project is 58637m2, with three floors underground and nineteen floors above the ground. The building height is 78.80m, and the total construction area of the basement is 16490m2. The main functional rooms of the basement are garage, air inlet and exhaust room, equipment room, staff canteen, kitchen, bicycle garage, staff bathroom, etc.
During the excavation process of the project, full-time surveyors are assigned to measure the elevation 300 mm from the trench bottom, nail a horizontal elevation stake on the trench side, use a 300 mm standard ruler to check the elevation of the trench bottom at any time based on the stake, and finally pull a straight line at both ends to check the size from the trench edge, determine the groove width standard, trim the trench side according to this, and finally remove the earthwork at the trench bottom.
Xx Jitailong Plaza Jinbi Brilliant Building is located in the B03 plot of xx Jinbi Road, with a total floor area of about 32422.36 ㎡, which is divided into shopping malls, residential buildings and underground garages.Among them, the first to fourth floors are shopping malls, and the first to third floors are world style squares with a building area of 14000 m2.
The wet operations such as ceramsite hollow masonry and plastering of this project are constructed by the ninth branch of Nantong Third Construction Co., Ltd., and the fine decoration in other rough decoration is constructed by professional decoration companies. Before construction, each subcontractor should understand their own work content in detail, and reasonably arrange the mobilization of various types of work and materials.
Xx Jitailong Plaza Jinbi Brilliant Building is located in the B03 plot of xx Jinbi Road, with a total floor area of about 32422.36 ㎡, which is divided into shopping malls, residential buildings and underground garages.Among them, the first to fourth floors are shopping malls, and the first to third floors are world style plazas with a building area of 14000 m2.
Light gray high-grade exterior wall paint is selected for this project.Before construction, the mortar and topsoil on the surface of the base course shall be cleaned.Before painting, the wall shall be watered and wetted first, and painting can be carried out after there is no water. The consistency of the paint is appropriate, and no thinner is allowed.
The main feature of the exterior wall decoration of this project is that there are many methods. The construction shall be carried out according to the elevation of the exterior wall and the detail node of the wall body. The surface tile coating part and the thermal insulation material shall not be lower than Grade B1, and each floor shall be provided with a fire barrier.The fire isolation belt shall be set with Class A insulation material with a width of no less than 300mm along the floor, and shall be fully pasted with the wall. See the attached figure for the method of fire isolation belt.(Refer to 10BJ2-11, G6 on page 34) The isolation belt material is RFT phase change energy-saving mortar.
The acceptance meets the excellent standard and does not fall short of the owner's expectations.Our company will organize the best project management team, dispatch a high-quality operation team that is skilled, disciplined, tempered by many large-scale projects and able to fight hard, and put into the construction of the project to organize on-site civilized construction, so as to ensure that the project meets the standard of civilized construction site.During the warranty period after the completion of the project, we will regularly and regularly provide quality services at any time;After the warranty period expires, our company will also try our best to solve the quality problems not caused by our construction to meet all reasonable requirements of the owner.The company is a Grade II qualification enterprise specialized in building decoration engineering, with rich experience and talents,
(7) If the color difference of the base course is large and the thin wallpaper that is easy to penetrate is used in the design, the base course should be treated afterwards to make its color consistent.(8) For rooms with high humidity and often wet walls, the base course should be moisture-proof before pasting, and waterproof wallpapers, adhesives and other materials should be used.(9) Technical measures and quality requirements shall be emphasized during technical disclosure to construction personnel.Before large-scale construction, the sample room shall be built first, and large-scale construction can be organized after the confirmation of the relevant parties.4) Construction process flow: base course treatment, painting sealing primer → puttying and leveling → hanging vertically, square setting, leveling, snapping lines → calculating materials, cutting paper → sticking
The construction organization design is specially prepared for interior decoration works, involving project overview, schedule, construction scheme, management personnel organization, quality assurance system, safe and civilized construction, finished product protection, etc.It is hoped that all relevant units will clarify the design and construction points of the interior decoration project, cooperate closely in the construction process, and complete the construction tasks on time with quality and quantity guaranteed as scheduled.
1. Ground: check the leveling of the base course, and chisel and repair the parts with large deviation first.The base course shall be rough and clean, free of oil stain, ground ash and ponding, especially white mortar ash and slag.After cleaning, water shall be sprinkled for wetting before plastering the base mortar, but there shall be no ponding on the ground.Before paving, the bottom layer shall be painted with plain cement slurry, which shall be integrated with the paved cement mortar.2. Wall surface: Before wall coating works, check the hollowing of the base or the missing edges and corners of the base, repair with 1:3 cement mortar, and fill the surface pockmarks and gaps with putty.Dust, dirt, splashes and mortar flow on the surface of the base course shall be removed.3. Installation of wooden door sleeve ① According to the design requirements, find the position and elevation in advance and snap the line. The wooden parapet can use 9X 25 (25X 30, 20X50) wooden keel with vertical and horizontal spacing of 400 (500), 300 (400). According to the keel partition size, use Φ 16~20Impact drill shall be used to drill holes with a hole spacing of 300 (400) and a hole depth of not less than 60. Wood wedges and iron nails shall be used to fix the holes. Damp proof course shall be made on the wall where the wall is prone to damp. Wood wedges can be painted with tung oil and dried before being punched into the wall holes.The wooden keel must be installed vertically, straightened and squared.The exposed part of the keel shall be painted with fireproof paint, and then the 5-9mm base plywood shall be nailed with gun nails on the wooden keel.② The panel shall be selected according to the wood with similar color in the adjacent parts before nailing, and no scratch glue is allowed on the panel surface.③ Trial assembly shall be carried out after the panel is assembled. Formal installation can only be carried out when the panel size, joint, wood grain and color look good. Generally, the root of wood grain is downward and symmetrical.If the panel is required to leave the seam, the stacker can be used to repair the straight seam slot.
Construction unit: School of Reliability and System Engineering, Beijing University of Aeronautics and Astronautics;Project name: Beihang Civil Building Decoration Project;Construction site: Xueyuan Road Campus of Beijing University of Aeronautics and Astronautics;Project scale: 3225m2.
Decoration works: indoor wall, ground, floor, dado renewal, staircase railing renewal, toilet redecoration of floors 1 to 4, including sanitary ware replacement of all internal doors, external doors and door jambs, classroom podium renewal, external wall coating, all steel components re painting, removal of the west screen wall, removal and replacement of the west iron shutter, removal and replacement of the west window of the second floor of the reading room, with 250mmThe thick aerated concrete block is used for plugging, the outdoor steps on the south side of the first floor are replaced, and the sunlight board above the original roof patio is removed and replaced with a new sunlight board.