Special construction of anti slide pile in highway engineering programme (Manual hole digging pile)
This project mainly refers to the landslide and accumulation caused by 5.12 Wenchuan Earthquake. There are 3 anti slide piles with a length of 30m and a section size of 2000mm * 1500mm. The retaining wall and lock opening are made of C20 reinforced concrete, and the pile body is made of C30 reinforced concrete. 2.2 Construction plan The construction period of this project is tentatively set as 30 days. According to the project characteristics, combined with the equipment and personnel conditions, in the actual construction, we strictly follow the construction organization design, reasonably arrange the construction machinery, personnel and time according to the construction period requirements of the Tenderee, and strive to complete the construction task in advance on the premise of ensuring the construction quality and safety. 2.2 Main material supply plan The mobilization plan of engineering materials such as steel bars, cement, sand, stone, etc. shall enter the construction site on time according to the construction period given by the Tenderee and the project progress. 2.3 Plan of main construction machinery and equipment Excavators, air compressors, electric welding machines, cutting machines, hand winches, bucket carts, steel bar butt welding machines, hammers, steel chisels, dustpans, site lighting and underground lighting, etc. shall enter the construction site on time according to the construction period specified in the contract and the project progress.