Construction organization design of a school group building in Chongqing
1. The preparation of the construction organization design is to provide a more complete programmatic technical guidance document for the construction project of the eighth bid section of the new campus construction project. During the construction implementation phase, it will be strengthened, refined, and properly adjusted on this basis to guide the construction more comprehensively and operationally. 2. Adhere to the capital construction procedures, organize the construction in strict accordance with the requirements of the bidding period, ensure the completion of the project within the bidding period, and give full play to the project benefits and capital construction investment benefits. 3. Reasonably organize the project management team according to the actual situation and scale of the project. Prepare project construction scheme, construction procedure, construction method, labor organization and technical organization measures. 4. Reasonably arrange the construction schedule, draw up the construction period network and overall construction schedule of each node process, and connect the time of divisional and subdivisional works. Specify the supply plan of labor, construction machinery, machines and tools, materials and various semi-finished products. 5. Strengthen planning in construction, overcome blindness, save materials, reduce costs, and complete construction tasks more quickly, better and economically on the premise of ensuring safe production and improving quality. 6. Strengthen the management of the general construction layout, reasonably arrange the construction site, plan the general layout and specific implementation of living, office and production houses, construction roads and large and medium-sized machinery, and make preparations in advance. 7. Actively promote the application of new materials, new processes, new technologies and new equipment, so that science and technology can be transformed into productivity.