Uploaded on: 2023-10-10 14:11:12
zero
5 points

The building of this project has been built for a long time, and now the original structural floor slab needs to be replaced and the overall reinforcement and transformation contents are as follows: 1. The first floor top timber floor slab is replaced with cast-in-place floor slab; 2. The building masonry wall is reinforced with double-sided concrete slab wall as a whole; 3. The beams and slabs of the original structure are strengthened by pasting carbon fiber; 4. The original structural column is strengthened by enlarging the section

Click to download the source file now

Special statement: This material belongs to the sharing uploaded by users Downloaded content, only for learning, not for commercial use. If there is any copyright problem, please timely contact Station delete!