Monthly supervision report of a factory building project in Tianjin
Safety production and civilized construction 1) Two minor accidents occurred this month. The safety protection of construction operation cannot keep up with that, and some high-altitude operators do not wear safety belts; Some mechanical protective covers on the construction site are incomplete; The supporting part of the dining room basement has been displaced, and the construction unit has been notified to carry out reinforcement treatment and strengthen future observation; The drainage system at the construction site is not perfect, and the temporary buildings are basically completed. Urge the construction unit to improve the above problems as soon as possible. 2) Civilized construction. The greening of the office area and living area is basically completed, all kinds of signs are basically complete, and the construction site is cleaned by a specially assigned person; The construction site basically achieves the orderly stacking of engineering materials, semi-finished products and components, the hardening treatment of some ground in the processing area and stacking area of materials has not been completed, and the identification of materials is incomplete; During the construction process, some construction working surfaces were not cleaned after the completion of construction Summary of supervision work of this month: the supervision work of this month focuses on the inspection and acceptance of mobilized materials. Review various construction organizations and plans submitted, review all subcontractors, and conduct on-site inspection when necessary. Check and accept the application for inspection of each subdivisional project. It is prohibited to use unqualified materials in the project and proceed to the next process without the acceptance of the previous process. Strengthen on-site patrol inspection and on-site supervision to control the construction quality of key parts and processes. The construction progress on the site this month is slow. Analyze the reasons and communicate with the construction unit in time to strengthen the control of the construction period. In case of delay, coordinate with the contractor in time and require the contractor to take measures. Assist the construction unit to do a good job in safety work at the site, stop violations in a timely manner, find potential safety hazards at the construction site, take precautions, and immediately notify the construction unit to rectify. Do a good job in coordination between Party A or other units and the Contractor. In a word, the supervision work of this month is in place. 6、 Key points of supervision work in the next month: continue to do a good job in the quality control and duration control of foundation and main works construction. From the site situation, duration control should be the top priority. Assist the construction company to organize the mobilization of personnel, machinery and materials, and assist the construction company to strengthen the management of the construction site to ensure the project progress. At the same time, assist the construction unit in the review and investigation of subcontractors, assist the construction unit in the management of project changes and negotiations, assist the construction unit in the safety and civilized construction of the construction site, strive for "Haihe Cup", and do a good job in the quality control and duration control of hydropower installation works Construction image progress of each discipline 1) Civil works: from April 25, 2008 to May 25, 2008, the following works have been completed; On May 6, the design, construction, supervision, Party A and the quality inspection station in the park accepted the bearing platform and the bearing platform beam of the battery plant and the complex building. The acceptance was qualified, and the anti-corrosion and backfill of the bearing platform and the bearing platform beam of the battery plant and the complex building were completed; The first floor roof formwork erection and rebar binding of the first section of the battery plant are in progress, the first floor full scaffolding erection of the second section, and the first floor column rebar binding of the third section; The concrete pouring of the first floor column and roof of the first section of the complex building is completed, and the second and third sections carry out the first floor roof formwork erection and rebar binding; On May 3, the foundation trench of the restaurant was excavated, and on May 6, the foundation trench of the restaurant was accepted. The acceptance was qualified, and the construction of the concrete cushion was completed. On May 9, the line inspection was planned, and the acceptance was qualified. At present, the construction of the basement of the restaurant is under way, and the construction of some bearing platforms, bearing platform beam reinforcement, and formwork above - 2.4 meters is under way About 7.54 thousand words