1. The electrical construction drawing design of the project includes lighting, lightning protection and protective grounding, telephone and cable television.
2. The load level of the building is Level III power supply. The power supply is led from the outdoor box transformer in the campus to 380/220V. The buried depth of the cable is 0.8m. Repeated grounding and protective grounding should be made at the place where the building enters. The grounding resistance is less than 1 ohm, which is shared with the lightning protection grounding system. The emergency lighting adopts the storage type emergency lighting, and the emergency lighting time is not less than 30 minutes.
3. Line laying: copper core plastic insulated conductor BV-500V is selected for general lighting lines, and it is laid in FPC pipes in a concealed manner. During construction, the route can be properly adjusted according to the actual situation.