The project is a three storey kindergarten, belonging to Class III building. Design scope: lighting distribution system; Lightning protection and grounding system. The power supply of the project is introduced from the substation of the residential area, and the incoming line is introduced through the PC pipe buried with VV22 cable. The unit cable terminal main meter box is set in the incoming building. The unit shunt distribution box is set in the front of the terminal main meter box, and the applied voltage is 380/220 V
The drawings include: electrical design description and legend, first floor lighting plan, second floor lighting plan, third floor lighting plan, first floor socket plan, second floor socket plan, third floor socket plan, power distribution system diagram, roof lightning protection plan, foundation grounding plan, first floor weak current plan, second floor weak current plan, third floor weak current plan, Weak current system diagram, etc.