This project is Xuchang Blue Coast Bathing Center, with six floors in total.
The bath center adopts central air conditioning, and the main difficulty of this project is the air conditioning design of the bath area.
The air conditioning water system adopts the double pipe same process system; Air conditioning cold and heat sources are uniformly provided by the refrigeration room of the VIP building. In summer, 7~12 ° C cold water is used, and in winter, 60~50 ° C hot water is used Air conditioning room adopts fan coil unit plus fresh air; The swimming pool adopts DC system; There are 8 fresh air systems in the whole building, X1-1 system~X4-3 system
This design includes the design of air conditioning and ventilation systems;