1、 Project overview:
The project is located in Shenzhen, with a total floor area of about 6200m2 and an air conditioning area of about 4800m2. The building has eight floors above the ground, and the above ground part is an office building containing offices, conferences, archives, exhibition halls and other functional rooms
2、 Cold and heat sources:
The cooling and heating sources of the air conditioners on the first and second floors of the project are provided by the multi split system
3、 Air conditioning system:
1. The fresh air required by the multi-function hall is absorbed and exhausted by the total heat exchanger, and the indoor return air is pressurized, cooled and dehumidified by the indoor unit, and then sent into the room by the side air supply outlet or diffuser.
2. Indoor unit plus fresh air system shall be adopted for the rooms with independent intervals in the first and second rooms
4、 Ventilation system:
1. The smoke control staircase near the outer wall adopts natural smoke exhaust, and the sum of the total area of openable external windows in every five floors is not less than 2.0 square meters.
2. The area of the openable external window shall not be less than 2% of the area of the room or aisle
There are 29 drawings in total.