home page » News Center » Industry News » Model of dust remover installation construction scheme

contact us

Service hotline: fifteen billion six hundred and thirty-nine million seven hundred and ninety-two thousand two hundred and eighty-nine
Address: Zhengzhou National High tech Industrial Development Zone
Tel./Fax: 0371-86686789
     

Choose us to design and select models for you

Model of dust remover installation construction scheme

24-06-27 Source: RCO catalytic combustion equipment, dust control equipment, environmental protection equipment manufacturer Zhengzhou Tengda Machinery

 

1、 Project Overview

Project Name: Dust Collector Installation Project of XX Company

Project location: Production workshop of XX company

Project objective: install dust remover equipment, reduce dust emission in the production workshop, improve the working environment, and ensure the health of employees.

2、 Preparation before construction

Confirm the model, specification and quantity of the precipitator equipment, and check whether the equipment is intact.

Prepare tools and materials required for construction, such as welding machine, screwdriver, electric drill, expansion bolt, sealant, etc.

Arrange construction personnel and clarify their responsibilities to ensure safety during construction.

3、 Construction steps

1. Dust collector foundation installation

(1) According to the equipment foundation drawing, mark the foundation position of the precipitator equipment on the workshop floor.

(2) Excavate the foundation pit as required to ensure that the size and depth meet the requirements.

(3) Lay reinforcement in the foundation pit and fix the equipment foundation.

(4) Pour concrete to ensure stable foundation.

2. Dust remover equipment installation

(1) After the foundation concrete is dry, move the dust remover equipment to the installation position.

(2) Use expansion bolts to fix the dust remover equipment and the foundation firmly.

(3) Connect the dust remover equipment and pipeline to ensure good sealing.

(4) Install the electrical control system of the dust collector, and conduct wiring and wiring according to the electrical drawings.

3. Dust remover pipeline installation

(1) According to the workshop layout and equipment location, plan the pipeline route of the precipitator.

(2) Use angle steel, supports and other materials to build pipe supports to ensure that the pipes are stable.

(3) Install the pipe of the dust remover to ensure good sealing at the pipe connection and avoid air leakage.

(4) The inspection door, cleaning port and other accessories shall be set at the proper position of the pipeline to facilitate the later maintenance.

4. Installation of electrical system of precipitator

(1) Install the electrical control system of the precipitator according to the requirements of the electrical drawings.

(2) Check whether the electrical components are intact and the wiring is correct.

(3) The electrical system shall be debugged to ensure the normal operation of the precipitator equipment.

4、 Construction safety measures

1. Construction personnel shall wear safety helmets, safety glasses, gloves and other protective equipment.

2. Safety warning signs shall be set up at the construction site to ensure safety during construction.

3. During the construction process, the safety operation procedures shall be followed, and illegal operations are strictly prohibited.

4. Regularly inspect the construction site to eliminate potential safety hazards in time.

5、 Construction acceptance

1. After the construction is completed, conduct a comprehensive inspection of the dust remover equipment to ensure that the equipment is installed correctly and operates stably.

2. Air leakage detection shall be carried out for the dust remover pipeline to ensure good sealing.

3. Test the electrical system to ensure normal operation.

4. Invite the Owner, Supervisor and other relevant units to conduct acceptance to ensure that the project is qualified.

6、 Post construction maintenance

1. Regularly maintain the dust remover equipment to ensure normal operation of the equipment.

2. Regularly clean the dust remover pipeline to avoid excessive dust accumulation affecting the dust removal effect.

3. Regularly check the electrical system to ensure safe and stable operation.

4. Establish a dust remover equipment file to record the operation and maintenance of the equipment and provide a basis for later maintenance.

The above is the model of the dust remover installation construction scheme, and the specific construction scheme shall be adjusted and optimized according to the actual project situation. During construction, the safety operation regulations shall be strictly followed to ensure construction safety. At the same time, strengthen the later maintenance management to ensure the normal operation and long-term stability of the precipitator equipment.

 

 

Previous:
No, it's the latest article

contact us

156-3979-2289 0371-86686789
Address: Zhengzhou National High tech Industrial Development Zone

Dithering to watch the on-site case

Scan the code to contact WeChat customer service

Copyright © 2017 All rights reserved RCO catalytic combustion equipment, dust control equipment, environmental protection equipment manufacturer Zhengzhou Tengda Machinery YICP Preparation No. 18002881 - 1
 Tengda Machinery Online Customer Service