(3) Construction deployment principle and construction sequence (1) Construction deployment principle: according to the characteristics of the project and the company's technical equipment and labor resources, the construction of the project is organized in the principle of underground first, ground first, civil engineering first, equipment first, structure first, decoration first, outdoor first, indoor first, wall first, ground first. Before the decoration construction, the sample room shall be built first, and the main structure construction