Construction period objective: carry forward the enterprise spirit of indomitable struggle and team work, and successfully complete the task on schedule. The planned commencement date is December 16, 2017, the planned handover date is March 15, 2017, and the planned construction period is 3 months. Among them, subgrade, small bridge and culvert works are planned to be completed on February 15, 2017; The pavement works are scheduled to be completed on March 1, 2017; Traffic safety