After the bidding of the bidding project is completed, the bid will be opened. The process of bid opening should be open to the public. The evaluator will evaluate the bid and determine the candidate for winning the bid after the evaluation. How can the bid inviter deal with any objection to the evaluation results of the project?
According to the relevant laws and regulations of our country, if the bidder or other interested parties have any objection to the bid evaluation results of the project that must be subject to bidding according to law, they shall raise it during the publicity period of the bid winning candidates.
For projects subject to tender according to law, the tenderee shall publicize the bid winning candidates within 3 days from the date of receiving the bid evaluation report, and the publicity period shall not be less than 3 days.
If a bidder or any other interested person has any objection to the result of bid evaluation of a project subject to tender according to law, it shall raise it during the period when the bid winning candidates are publicized. The tenderer shall reply within 3 days from the date of receiving the objection; Before making a reply, the bid invitation and bidding activities shall be suspended.
Legal basis
Article 54 of the Regulations for the Implementation of the Law of the People's Republic of China on Tenders and Bids, for projects subject to tender according to law, the tenderee shall publicize the candidates for winning the bid within three days from the date of receiving the bid evaluation report, and the publicity period shall not be less than three days. If a bidder or any other interested person has any objection to the result of bid evaluation of a project subject to tender according to law, it shall raise it during the period when the bid winning candidates are publicized. The tenderer shall reply within 3 days from the date of receiving the objection; Before making a reply, the bid invitation and bidding activities shall be suspended.