(1) The basic theory of construction project supervision is the theoretical basis for solving the practical problems of supervision, such as the means of target control, risk management, the setting of supervision organizations, supervision specifications, safety production, file management, etc. Note: national laws, regulations and relevant regulatory documents issued by the competent construction department shall prevail. For example, the supervision specifications, safety production regulations and other documents, if the teaching materials conflict with the documents, in principle, the supervision specifications, safety production regulations shall prevail.
(2) The Code for Construction Project Supervision and the Regulations on the Administration of Safe Production of Construction Projects are highly operational examination contents, which should focus on the actual operation procedures and methods. This document is the most important document. Many of the answers to the examination standards are original documents, and many terms need to be understood and remembered.
It is specified in the examination outline that supervision laws and regulations will be taken as important examination contents. The review should focus on the understanding and practical application of regulations.
2. Second subject
The key point of contract management is the application of the contents of construction contracts and supervision entrustment contracts in cases, which are mostly used to claim compensation and clarify responsibilities. For example, the handling of force majeure, the re inspection of concealed works and other issues should be done according to the contract, and some procedures and time requirements agreed in the contract are also very important. For example, I have tested the processing procedures after the discovery of ancient tombs.
3. Third subject
(1) "Three Controls" is naturally also the focus of the exam. Quality control, investment control, progress control, calculation, and the application of network chart in claims, investment control, progress control, and construction organization. Preparation of bill of quantities. Capital equivalent calculation and evaluation basis, etc. In the three controls, many of them are instrumental knowledge that must be mastered and flexibly applied.
(2) The Regulations on the Quality Management of Construction Projects is also an important part of supervision case assessment, which is mainly about the quality responsibility of all parties. It often occurs in claims, quality accidents and quality problem handling procedures.
(3) There is also the Bidding Law, which is mainly used to determine the contract, and its procedures and practices should be mastered. The most common question is to pick mistakes. It is suggested to study the Bid Evaluation Committee and Bid Evaluation Methods carefully. Most of the teaching materials are explanations of this document. It is suggested to read the original text.
(4) In the specific practice of local supervision work, some specific operating procedures and methods may also be different, but the review preparation should be based on the corresponding contents and methods specified in the teaching materials, laws, regulations and specifications.
In terms of the assessment content, the basic content required in the Examination Outline is the main content. The supervision work is management work, not technical work, and the examination will not involve very professional technical content.