When it comes to the installation of charging posts, I believe that the first contact with friends will be a little strange. If you want to install a charging post, it is necessary to understand the various procedures to avoid causing yourself a lot of unnecessary trouble. Now let's follow the small editor to find out what procedures are required to install the charging pile?
1. Obtain the installation permit of the property
After showing the property the need to install the charging pile, a staff member will go to the parking space with the owner to check whether the parking space meets the installation conditions. If the conditions are met, a guarantee letter needs to be signed to ensure that the fire safety and circuit safety of the community will not be affected during and after the installation.
2. Reported installation of electricity meter
There are roughly four kinds of materials to be prepared: 1. ID card; 2. Property consent certificate; 3. Parking space use right certificate; 4. Charging facility installation registration certificate. After the materials are prepared and sealed, they will be submitted in the State Grid app and the Southern Power Grid applet. The power supply department will send regional specialists to visit the site to survey and confirm the scheme for installing electricity meters, and then the power supply bureau will send regional specialists to visit the site to install electricity meters. (It is difficult to estimate the interval between two visits of the power supply bureau, which depends on the busy degree of the local power supply bureau)
Identity certificate: if you have a copy of your ID card, you can use a copy of your account book if you don't have one.
Property consent certificate: find the property in the community to apply for the installation of the template of the charging pile Electric Vehicle Charging Facility Safety Management Agreement (not necessarily the name, or depending on the property). If the property does not have a template, it will be provided by the charging pile installation service provider, and then ask the property to seal the agreement to confirm that it agrees to install.
Parking space use right certificate: the parking space purchased by oneself is the parking space property right certificate or the invoice for purchasing parking space; If it is a leased parking space, the property will issue a parking space use certificate if it is leased to the property, and the neighbor will provide a parking space ownership certificate or purchase invoice if it is leased to a neighbor, as well as the parking space lease agreement between you and your neighbor.
Charging facility installation registration certificate: The charging pile service chamber will provide the Charging Facility Installation Registration Certificate. If the local power supply bureau requires the registration certificate to be stamped by the manufacturer, it will get the stamped form; If there is no requirement, you can get a blank form, fill in the form and submit it to the power supply bureau.
3. Application for installation of charging post
You can apply for installing the charging pile on the mobile phone app and official website of the corresponding brand, or directly contact the after-sales staff. You need to submit the property permit and the photos after the installation of the electricity meter, and then make an appointment for on-site installation. Usually, the installation master will survey on the site first, and then give a construction plan.