Current location: home page >> Procuratorial window
Procuratorial window
[Year of Excellence in Law Enforcement and Justice] Prosecutors' Story of "Yixin for the People" | Prosecutors went to the scene three times to investigate this matter
Time: April 9, 2024 Author: News source: [Font size: large | in | Small

In January 2024, citizen Xiao Wang (a pseudonym) said: "There is a construction site under my house that has stopped working. I can't see people on weekdays, but there are a large number of building materials, sand and stones piled up in the open air. The New Year is coming, and this looks ugly. When the wind blows, there is ash everywhere, which is bad for people's bodies."


01

After receiving the clue, Yijiang District Procuratorate believed that there might be potential dust pollution at the scene, and started the public interest litigation procedure on January 26, and for the first time We went to the scene to investigate and found that the information reported by the citizens was basically true. The prosecutor believes that this may not be an accident. As the Spring Festival holiday approaches, the construction site will be shut down one after another, and at least rest until the 15th day of the first month. It is urgent to do a good job of dust pollution prevention during the Spring Festival.


02

From January 29 to January 30, the Prosecutor The second time Arrived at the site, visited 9 construction sites in the region, conducted a comprehensive investigation on the dust pollution, and passed the inspection proposal on January 31, transferring all the problems found to the competent unit of the construction industry for handling. After receiving the procuratorial suggestions, the administrative organ completed all the supervision and rectification work in just one week before the Spring Festival holiday, and gave preliminary feedback to the procuratorial organ on the rectification.

Click the picture to view the comparison before and after rectification


03

On March 20, the Yijiang District Procuratorate, together with the competent unit of the construction industry, carried out a look back action to look back on the treatment of dust pollution at the construction site. This is the prosecutor third time When we arrived at the scene, we saw that the problems mentioned in the procurator's recommendations, such as the inadequate coverage of the filter screen, the imperfect spray of fog guns, and the construction waste not being cleared and transported in time, were rectified one by one. The procurator was relieved, told the relevant situation to the citizen Xiao Wang (a pseudonym), and was praised by the masses.


Prosecutor's hint

According to the provisions of Article 69 of the Law of the People's Republic of China on the Prevention and Control of Air Pollution, the construction unit shall set up hard fences at the construction site, and take effective dust prevention and dust reduction measures such as covering, subsection operation, timing construction, watering for dust suppression, and washing the ground and vehicles. Construction earthwork, engineering waste and construction waste shall be cleared and transported in a timely manner; Those stored in the site shall be covered with closed dust-proof net. Engineering waste and construction waste shall be treated as resources. The construction unit shall strictly implement dust control "Six hundred percent" 的要求,做到 "100% standard of construction enclosure", "100% wet work on construction site", "100% hardening of construction roads", "100% coverage of material stacking", "100% washing of vehicles in and out", "100% closed transportation of muck vehicles"


The windy spring is the high season of dust pollution. All construction units must strictly implement the "six hundred percent" requirement for dust control. If the general public finds relevant problems, they can report them to the procuratorial organ through the "public interest litigation snapshot" small program or call 12309.