Leakage repair and pollution of underground garage in Jiujiang County Water pipe Leakage stoppage in the tunnel and leakage repair in the basement, The waterproof grade of the basement of the project is Grade II, and three layers of waterproof are adopted. The floor and exterior wall are rigid waterproof with C30S8 waterproof concrete, and two layers of 3mm thick external waterproof are applied SBS Type III modification asphalt Waterproof roll (Flexible waterproofing), the peripheral backfill adopts 2:8 lime soil three layers of waterproofing. In order to ensure that the basement waterproof is foolproof, we should take every waterproof seriously.
Compilation basis: Unified Standard for Construction Quality Acceptance of Building Engineering (GB 50300-2001), Code for Quality Acceptance of Underground Waterproofing Engineering (GB 50208-2002), Code for Construction Quality Acceptance of Concrete Structure Engineering (GB 50204-2002), Code for Construction Quality Acceptance of Building Ground Engineering (GB 50209-2002), Code for Indoor Environmental Pollution Control of Civil Building Engineering (GB 50325-2001) Standard for Quality Review of the Great Wall Cup Project of Building Structures (DBJ / T01-69-2003)
Basement plugging base requirements:
(1) Trench inspection: the foundation trench has passed the acceptance of the design, survey, owner, supervisor and other units, the base treatment meets the design requirements, and the concealed acceptance records have been handled
(2) Setting out and leveling: according to the measurement and positioning control line, set out the cushion sideline and the position line of Houjiang belt.
(3) Make elevation control points: according to the design elevation, use cement mortar to make several elevation control points in the middle.
Requirements for leak stopping materials in basement:
(1) The project adopts premixed concrete and pump pouring; When signing the concrete supply contract with the concrete company, the following technical requirements for waterproof concrete are proposed as part of the contract: a Concrete grade: C39S8b Slump: 100-140mmc Initial setting time: 4-6 h, d. Control requirements for alkali aggregate: large chloride ion content 0.2%, large alkali content 3.0 kg/m3.
(2) Before concrete mobilization, the concrete company shall provide concrete mix proportion notice, calculation sheet of chloride ion and alkali content, concrete setting curve table and other data, which can be officially poured after being reviewed by the project chief engineer and supervision engineer.
(3) Control the quality of concrete entering the site: after the concrete enters the site, check the time of concrete leaving the machine in a timely manner, make a record of the time of starting pouring and finishing pouring, and ensure that the concrete is poured before the initial setting. During pouring, the tester shall check the slump of each truck of concrete entering the site, make records, and withdraw the unqualified concrete from the site.
Quality acceptance of basement plugging
(1) Division of inspection lot: confirm the division of inspection lot and inspection quantity with the supervisor before acceptance. According to the specification requirements: spot check every 100m2 of exposed concrete area, 10m2 for each place, and no less than 3 places; Check all details.
(2) Acceptance: see the section Management Assurance System and Quality Management Measures for details.
(3) Inspection of technical data a. Concrete certificate, impermeability test report and alkali content report provided by the concrete company.
Jiangsu Sanligang High Altitude Building Anticorrosion Co., Ltd. - * * * Leak stoppage company, leak stoppage unit, undertaking various waterproof and leak stoppage projects, leak stoppage of sewage pool expansion joint, leak stoppage of sewage pool, leak stoppage of underground garage, leak stoppage of sewage pipe, leak stoppage of basement, cable trench, leak stoppage of hydropower station basement, leak stoppage under pressure, leak stoppage of basement, leak stoppage of pool, leak stoppage of mine Tunnel plugging project, cable trench plugging project, expansion joint plugging project, elevator shaft plugging project, coal gallery plugging project, highway tunnel plugging project, subway tunnel plugging project, underground tunnel plugging project, pump house plugging project and other plugging projects. The registered capital of the company is 11.086 million yuan, and the working capital is more than 80 million yuan; It has a technical construction team of * * *, including 36 people with * * * professional titles and 126 people with intermediate professional titles. With Grade I anti-corrosion qualification, Grade I safety qualification and Grade II building qualification, the company has five branches and eighteen offices. The company has strong technical force and focuses on the training of waterproof technicians. At present, it has * * * leak stoppage engineering technology * * *, construction management personnel, advanced construction technology and technology and * * * construction team, For more than 40 years, * * * has been committed to the research and development of construction technology and materials for building waterproof and leak stopping. With the progress of science and technology, in recent years, the company has introduced foreign advanced waterproof and leak stoppage technology with pressure, impermeability and vibration resistance, adopted * * high-tech nano molecular waterproof materials, * * * prepared a new process of scientific pressure reducing grouting, * * * treated various underground engineering leakage, especially for massive concrete crack leakage, water tunnel engineering, settlement expansion joint leakage and leak stoppage With years of experience in maintenance and handling, the company is fully capable of difficult waterproof and plugging. The company adheres to the corporate style of "unity and hard work, forge ahead, rigorous and realistic, and hard work", and constantly blazes new trails. Relying on strong strength, scientific management and quality service, the company firmly adheres to the corporate purpose of "honesty and realism, serving the society, reputation, and users first". Act according to the modern enterprise management mode. According to the requirements of the Provincial Department of Construction, the Municipal Construction Commission, Party A's unit and the environmental protection department, the company has a hard target of civilized construction, quality * * *, lifelong responsibility and zero accidents. The construction personnel shall hold the "special industry technical operation qualification" issued by the Ministry of Labor of the People's Republic of China, and all of them shall participate in life insurance, so that the construction unit will have no worries. We are willing to work with our domestic colleagues to make our due contribution to the innovation and application of China's waterproof plugging technology. We sincerely welcome all enterprises and individuals to call us for consultation and negotiation. Give us a trust and we will give you a satisfactory answer. Business consultation