In order to promote the development of management case teaching and case study in the School, promote the development and sharing of local cases in China, and improve the quality of talent training in the School of Economics and Management of Beijing Jiaotong University, the case development management method is hereby formulated.
1、 Project establishment
(1) Application object and project establishment procedure
It is mainly for teachers engaged in education in our school. The case center is responsible for organizing the implementation and project management of the application, review and project establishment once a year.
(2) Project management
1. The project funds shall be checked and approved at one time, allocated by stages, used for special purpose, and the overspending shall not be supplemented.
2. The case developer is responsible for grasping the overall level of the project and the progress of research and practice. Timely summarize the research of the subject, and submit the stage progress report and conclusion report.
2、 Closing
(1) Conditions for applying for closing
1. The final result is completed by the case developer as the first signatory, and there is no dispute on intellectual property rights;
2. All officially published or published project achievements shall be marked with the words "Project Funded by Case Sharing Center of School of Economics and Management of Beijing Jiaotong University" (including title and approval number) in a prominent position, and those not marked shall not be recognized.
(2) The case developer needs to submit the following materials to apply for closing
1. According to the attachment four Write normative case text and case instructions based on the case structure.
2. Submit the text of the case and the paper version of the case instructions five Copies and electronic version( Word Format);
3. Power of attorney of the enterprise, power of attorney of the author, and other achievements of the project one Sets.
(3) Closing requirements
1. The subject case was completed on schedule and approved by two-thirds of the members of the expert review committee.
2. Delayed items: If the case results are completed on schedule, and more than half of the members of the expert review committee but not two-thirds of the members agree to pass, they can be postponed to the next year.
3. Not closing the project: the project case results were not completed on schedule.
(4) Under any of the following circumstances, the item shall be withdrawn:
1. Unauthorized change of project principal or subject name and basic content;
2. Failing to complete the agreed tasks as scheduled in the research cycle, and still not completed after two applications for extension;
3. The appraisal and conclusion of the two applications were not passed;
4. The project achievements have serious political problems or serious academic misconduct;
5. Violating regulations and practicing fraud in the process of project identification and conclusion.
If the above conditions are met, the project responsible person can voluntarily apply for withdrawal. The Case Center will circulate a notice of criticism on the cancelled projects and order them to recover the allocated funds; Case Developer three The case center project shall not be declared within the year.
enclosure:
1. Project initiation application form [Click to download]
2. Letter of Authorization [Click to download]
3. Author's Authorization [Click to download]
4. Basic structure and requirements of the case [Click to download]
5. Submission procedure of closing materials [Click to download]
Case Sharing Center of School of Economics and Management, Beijing Jiaotong University