Jiangxi Jinxian: The hot work of the "West East Gas Transmission" natural gas pipeline of the national pipeline network was successfully implemented _ Financial Online
home page gold >Body

Jiangxi Jinxian: The hot work of the "West East Gas Transmission" natural gas pipeline of the national pipeline network was successfully implemented

On the morning of May 17, the hot work for the reconstruction of No. 4 Valve Station of Nanchang Shanghai Branch Pipeline of the National Pipeline Network West East Gas Transmission Project was successfully implemented in Zhalan Village, Zhanggong Town, Jinxian County, Jiangxi Province. In this operation, the 4 # Valve Station of Nanchang Shanghai Branch Pipeline of the Second West to East Gas Pipeline will be connected with the DN200 pipeline already built in Jinxian Off load Station of the Pipeline Branch of Jiangxi Natural Gas Group Company by hot work. After the connection, it will supply gas for Jiangxi Guoneng Gas Co., Ltd. Off load, and bring benefits to the green development and people's life and production of Jinxian County.

At 7:10 am that day, with the vent valve of 4 # valve chamber slowly opening, the pipeline pressure slowly dropped to 0 MPa, and the nitrogen injection truck replaced the pipeline from the nitrogen injection port of 4 # valve chamber through the nitrogen injection equipment. After the gas detection is qualified, the operators concentrate on cutting and disassembling the 8 welded junctions, and lifting, polishing, assembling, demagnetizing and welding the prefabricated pipe section as a whole. Each process shall be carried out in strict accordance with the requirements of the hot work plan, and the on-site quality and safety management shall be in order. Personnel from Nanchang Gas Transmission Branch of West to East Gas Pipeline Project, Pipeline Branch of Jiangxi Natural Gas Group Company, construction, supervision, testing and other units strictly implement the epidemic prevention and control requirements to ensure the safety and control of the operation process.

"The project has basically come to an end since it started on March 8. After the hot work is completed, 95% of our project will be completed. As long as the hot work is qualified, we can connect with the national pipeline network of natural gas." Wang Qizhu, project manager of PetroChina Construction Engineering Co., Ltd., said.

It is understood that the opening and unloading project of the national pipeline network "West East Gas Transmission" natural gas pipeline is a major project being promoted by Jinxian County to benefit the people, which can further reduce the cost of gas consumption in the pipeline radiation area, effectively alleviate the problem of insufficient gas supply in the area, effectively guarantee and improve people's lives, alleviate the pressure of natural gas supply in the county, and make gas consumption more affordable for people and enterprises, It is of great significance to promote the green development of Jinxian.

"The opening of the West East Gas Pipeline is a major infrastructure construction in our county that is related to the national economy and the people's livelihood and the development of enterprises. After the ventilation, first of all, the price of gas used by enterprises and residents has been greatly lowered, and secondly, there are many advantages in the construction of ecological civilization and green development." Zou Chen, deputy director of the Development and Reform Commission of Jinxian County and director of the Energy Bureau, said.

label: Jiangxi Jinxian West East Gas Transmission Project of National Pipeline Network Hot work of natural gas pipeline Zhalan Village, Zhanggong Town